Berm Restoration – Repair dredge spoil containment berm. Timeline: mid-late June 2024 – July 2025
Shoreline Restoration – Install log-toe sills along the eroding Carr Creek shoreline. Timeline: May - Sept 2024.
Invasive Control/Marsh Planting –Removal of invasive plants with replanting of native species of marsh plants. Timeline: Summer 2024-25.
Tree Planting – The planting project is an environmental mitigation project associated with a development project on another portion of the installation. Trees, shrubs, and herbaceous plants are being planted to protect and restore an area that was cleared of invasive species.
Timeline: May – mid June 2024. The planting plan was submitted to MDE’s Critical Area Commission (CAC) office via email on 8 May 2024. Planting received CAC concurrence 14 January 2021, provided MDE was notified of the Planting Plan (sent 8 May 2024). Public notice of this project was issued in a news story on April 11, 2024, which can be found at the following LINK.